Project Budgeting & Budget Validation
Overview
Project Budgeting in DIGITZ ERP is performed after project creation and establishes the planned cost limits for the project across the three core cost categories that directly affect project execution:
- Purchase (Material & subcontract procurement)
- Expense (Operational, indirect, petty cash, service-related)
- Labour (Timesheet-based labour cost)
This budget forms the financial baseline for the project.
During execution, DIGITZ ERP performs real-time validation on every project-related transaction to ensure that actual cost does not exceed the approved budget. This prevents uncontrolled spending, avoids cost overruns, and enforces strict project cost discipline.
Purpose
To set total planned cost limits for Purchase, Expense, and Labour, and to ensure that every actual transaction posted against the project remains within approved limits—either by warning the user or blocking the transaction based on company policy.
This ensures complete financial control and ensures the project remains profitable throughout its lifecycle.
Budget Categories
DIGITZ ERP supports budgeting across the following fixed categories:
1. Purchase Budget
- Covers material procurement, subcontracting, external services.
- Based on BOQ, Estimate/Costing, or internal planning.
- Updates automatically when users post:
- Purchase Orders
- Purchase Receipts
- Purchase Invoices
2. Expense Budget
- Covers operational expenses such as:
- Petty cash
- Travel
- Tools and consumables
- Indirect service expenses
- Reduced by:
- Expense Entries
- Additional Expenses
3. Labour Budget
- Based on estimated manpower usage.
- Can be defined using:
- Total estimated labour hours
- Role/employee hourly rate
- Reduces automatically from:
- Timesheet entries
- Labour cost allocations
Budget Approval & Control
- Budget can be reviewed and approved internally before project execution.
- Once approved, it becomes the baseline.
- System can optionally alert when nearing budget limits.
Automatic Budget Impact
Every project-related transaction updates actual cost automatically:
Purchase Actuals
- Purchase Order
- Purchase Receipt
- Purchase Invoice
Expense Actuals
- Expense Entry
- Additional Expense
Labour Actuals
- Timesheet posting
- Labour calculations
These actuals are continuously compared against the approved budget.
Real-Time Budget Validation During Transactions
DIGITZ ERP validates all financial and operational transactions in real time.
Validation Logic
During a transaction, the system checks:
Actual Cost (spent so far)
- New Transaction Amount
Budget Amount
If this condition is true, the system takes action based on configuration.
1. Purchase Budget Validation
Triggered during:
- Purchase Order
- Purchase Receipt
- Purchase Invoice
If exceeded:
- System warns or blocks based on settings.
2. Expense Budget Validation
Triggered during:
- Expense Entries
- Additional Expenses
- Petty cash expenses
If exceeded:
- System alerts or refuses submission.
3. Labour Budget Validation
Triggered during:
- Timesheet entry
- Labour cost updates
If exceeded:
- System warns or blocks depending on company policy.
Validation Modes (Configurable)
A. Soft Validation (Warning Only)
- Allows the transaction.
- Warns the user that budget is exceeded.
- Useful for flexible operations or urgent requirements.
B. Hard Validation (Block Transaction)
- Prevents saving or submitting the transaction.
- Enforces strict cost control.
- Recommended for contract-driven, margin-sensitive projects.
Real-Time Monitoring & Reporting
All validated and posted transactions update:
- Budget vs Actual Report
- Project Profitability Report
- Project Progress Report
This ensures continuous visibility, accurate forecasting, and total project financial control from start to finish.